Hexcel Corporation

Project Details

Location: 6700 W 5400 S, Salt Lake City, UT 84118
Date of Completion: September 2012
Contract Amount: $ 2,728,000

Contracting Company: Layton Construction
Estimator & Project Manager: Jeff Otto

Hexcel Corporation was a new, 134,200 square foot, carbon fiber, pre-preg building for five manufacturing lines.  Included, were spaces for manufacturing, a large 11,000 square foot 10-degree freezer, as well as office areas.  The project included the installation of a new 46KV 10MVA Substation and new 15KV distribution.  The building is powered by four 4,000A Services. Special systems included hydronic underfloor heating systems, and a large fine particle dust collection system.  The project was budgeted based on a program supplied by the owner and user interface meetings.  The cost increase was due to scope changes including the addition of a 5th 4000A service.